Two timber contractors split the production and assembly tasks for the 286 room modules. Prefabrication in the workshop took three months. Installing the entire timber structure was completed in four months.

Two timber contractors split the production and assembly tasks for the 286 room modules. Prefabrication in the workshop took three months. Installing the entire timber structure was completed in four months.