Areas of paving had to be removed to erect the two steles. The elements were assembled lying on the ground. When the 8 mm Corten steel panels had been welded together the steles were tilted into the vertical and then bolted to the foundations.

Areas of paving had to be removed to erect the two steles. The elements were assembled lying on the ground. When the 8 mm Corten steel panels had been welded together the steles were tilted into the vertical and then bolted to the foundations.