Roof construction for the central axis of the Expo 2010 Shanghai

The greatest world’s fair to date welcomes its visitors with an impressive symbol – the central Expo Axis with its unique roof construction. The 1 km long and 100 m wide Expo Axis features pedestrian areas on four levels and is covered by a 65,000 m² membrane roof supported by 19 interior columns, 31 exterior pylons, and 6 funnel-shaped elements made of steel and glass with a doubly curved freeform frame structure. The so-called ‘Sun Valleys’ introduce daylight into the levels below and provide orientation within the huge complex. The concept of a built landscape with flowing transitions between interior and exterior called for a roof construction that expressively symbolises openness. This was realised by using a membrane consisting of fibre glass mesh with PTFE coating, a technology that allows creating spans of up to 100 m. Structural considerations significantly influenced the form finding process for the roof system. Three of four levels are directly accessible from the exterior. Only the lowest level with its three metro stations is centrally accessed and enables experiencing the entire length of the building. Vertically interconnected functional areas such as shops, staircases, and alternating use of materials structure the interior space. Most of all, the walkable Sun Valleys are places of relaxation. With their dynamic and ascending forms, they create naturally illuminated areas also in the lower levels. Successions of plazas, alleys, and gracious boulevards are intended to convey the quality of a continuously evolved urban structure and create a relation between the dimensions of the building and the human scale. Although the client formulated no requirements for sustainable use of energy for the Expo-Axis, the architects decided to adopt the world’s fair motto “Better city, Better life” for the project and develop a comprehensive ecological and energy concept while using natural resources. The building is supported by more than 3,500 piles, half of which are used for geothermal purposes. Further, a stormwater container with 200,000 l capacity supplies water for restrooms and irrigation of green spaces via filter and pressure booster units and is located beneath each of the six Sun Valleys. In the case of fire hazards, sprinklers as well are supplied with stormwater. Further components of the energy concept include cogeneration and LED lighting.

Roof construction for the central axis of the Expo 2010 Shanghai
© Christian Schittich

Form

The six Sun Valleys are funnel-shaped elements made of steel and glass with a polygonal mesh freeform frame structure. The diameter at their base is approximately 16 m and expands to widths from 70 to 90 m at their upper rim. They cover an area of approximately 5,000 m² each, optimized according to structural and design characteristics in numerous developmental steps. Their frame structure comprised of triangular shapes is comparable, in a similar way as the membrane roof, to natural structures – i.e. based on reduction of material resources.

Structure

The structure is the result of two basic considerations – for one, the geometry requires an increase in the number of triangular shapes from bottom to top. The alignment as well follows the main direction of force in order to create a polygon mesh structure of maximum efficiency. This is why the alignment is vertical at the structure’s base and ring-shaped at its upper rim. Therefore, instead of using 6 way nodes, special 5 and 7 way nodes are included at mid-height to produce a 30 degree rotation of the mesh structure. Location and number were defined in order to maintain the homogeneity of mesh sizes of approximately 2.20 m. The Sun Valleys need to bear dead loads, snow, wind, and earthquake impact, and also membrane loads of the PTFE coated fibre glass mesh. In order to determine the strength of the membrane, at first calculating the spring stiffness of load transmission points along the Sun Valley was necessary. The results of this calculation were then used for determining necessary steel profile sizes.

Optimisation

The strong loads originating in the local distribution points of the membrane are, thus, only recognizable in the increase of steel profile sizes within four segments surrounding the connecting points. Here, the general profile size of 180 by 65 mm is increased to 500 by 140 mm. Members were grouped according to their load bearing properties and profile sizes were optimised correspondingly. This resulted in the development of 48 different steel hollow profiles consisting of longitudinally welded flat steel elements. A precise adaptation to the individual load situation is achieved by gradually decreasing the gauge of flat steel elements. Thus, solid profiles also find use where required. The maximum elastic deformation was determined in cooperation with local experts.

Structural concept

The membrane roof covers an area of 65,000 m² and consists of a PTFE coated fibre glass mesh of the strongest type V with a tensile strength of 160 kN/m. The minimum level of prestressing is 2.5 kN/m. The structure is characterised by the exterior pylon high points as well as the low points at interior columns as connecting points for suspending the textile mesh. These are complemented by wind suction cables in the membrane plane, corresponding hangers that prevent the membrane from collapsing, and connecting cables to the exterior pylons.

Construction

The interior columns, 750 mm in diameter, bear the majority of vertical loads and are connected to the exterior pylons through wind suction cables. A compression ring connects main membrane and anchor cables to the interior columns. The main membrane loads are distributed into the pylon high points along the exterior. These are secured externally by two tie-back anchors with diameters of up to 160 mm. Gravity foundations on piles provide the necessary mass to bear tensile loads of, in part, far above 10,000 kN. The 2 by 2 m base plates of the return anchors permitted tension adjustment via threaded bars in the first months of spreading out the membrane. A special challenge was posed by establishing controlled load bearing of anchors and pylon bases, since every change in geometry also resulted in a change of load transmission within the membrane. Membrane or cable failure and resulting slacking can be ruled out, even in the case of heavy wind impact. The prestressing was optimized within a complex developmental process. The low points of the interior columns are the points where the greatest vertical loads are concentrated. Two layers of fibre glass mesh are necessary in these areas. Both layers are laminated and form a rosette shape. Numerous geometric optimisations ensure that radial forces don’t exceed peak limits and that a minimum level of tension is maintained within the ring in order to prevent membrane creasing. Along each Sun Valley, the membrane is connected in two to three points in order to fit it tightly along the funnel shapes. Double joint connectors prevent the transmission of unwanted moment forces resulting from changes in cable inclinations due to wind impact. The ball bearing mounted interior columns are equipped with individual pylon heads. Their shaft is comprised of a single component with up to 2 m long splicing plates. The large lengths produce significant local moments due to cable and axial deflection that needed to be determined for every single column head. Membrane drainage is integrated into the interior columns. The main membrane is connected to a compression ring at the top of the interior columns. Coping strips cover these connections and ensure seamless drainage. A further membrane of type II, significantly less stiff, comprises the connection between underside of compression ring and interior drain. Due to typhoon hazards typical for Shanghai, loads and deformations caused by wind impact were a crucial factor. In extensive wind channel experiments and via a more than 20 m long model of the roof construction, various loads and impacts were simulated at Tongji University. These complementary experiments are surprising and enriching for European engineers who, for the most part, rely only on computer calculations.

Architecture
SBA Architekten
Location
Expo Area, Shanghai (CN)

  • Paul Van Ostaijen Culture Campus in Leuven

    Lava architecten transformed an old mission building in Leuven into a place where circus arts, music, theatre, and dance coexist under one shared roof. Effective soundproofing is the precondition for the shared use of the facility.

  • The Lost Shtetl Museum in Lithuania

    The Jewish Museum in Šeduva commemorates the culture of Eastern European towns before World War II. With their building, Lahdelma & Mahlamäki Architects from Finland reimagine the small-scale structure of one such village. Its residents were murdered in 1941 by Nazis and their local collaborators.

  • Resembling a bridge, the scaly armour of the UCCA Clay Museum spans across the passageways to the neighbouring buildings. Where this structure touches the ground, Kengo Kuma & Associates arranged shallow water basins.

    Museum of Ceramic Art in Yixing

    The new UCCA Clay Museum advances the millennia-old tradition of artisanal ceramics the Chinese metropolis Yixing is renowned for. An armour of red clay tile encloses the exhibition spaces and the open timber roof constructions above them – an expressive space for the presentation of modern ceramic art.

  • The fly tower of the Glasshouse Theatre consists of textured prefabricated concrete elements, while the ­existing QPAC displays smooth in-situ concrete. The continuity of colouration, however, is clearly visible.

    Glasshouse Theatre in Brisbane

    The Glasshouse Theatre adds a fifth venue to the heritage-listed Queensland Performing Arts Centre. It can be flexibly used for concerts, operas, and dance and theatre performances. The glass facades of the deeply cantilevered foyer visualise the theatrical art of illusion on the exterior.

  • The monastery originally comprised four wings and a cloister. In the south, a squat church with a single nave connects to the complex. The head building with its three apses, a bell tower, and a transept were added in the 13th century.

    Monastery of Santa María of Sijena

    In their restoration of the Monastery of Santa María of Sijena, Pemán y Franco and Sebastián preserve traces of destruction, rebuilding, and decay spanning 800 years. Recently, they remodelled the east and north wings into an exhibition space for the convent’s valuable artworks.

  • The medical facility features a separate entrance in the east. A pergola made of prefabricated concrete elements welcomes the clients.

    Overnight Shelter and Medical Facility in Munich

    Housing for the homeless often consists of stacked contain ers. While the overnight shelter designed by Hild und K utilises prefabrication, thoughtful details adorn the robust building through which the Munich-based office conveys impres sions of warmth and home.