Power Plant in Düsseldorf

Stadtwerke Düsseldorf, the city’s public utility company, operates a modern, highly efficient power plant on its Lausward site, which is surrounded on three sides by the Rhine and lies directly adjacent to existing power plant units. The architectural theme for the new build resulted from a facade design competition held by the city: a series of tall frames form the visible envelope of the whole plant and bring them together to create the overall form. Groups of similarly sized elements make the power plant components beneath legible, while special frames add excitement and rhythm to the elevation. The most prominent and largest element is a stack enclosure, which is glazed on two sides and carries a visitor platform at 40 metres above ground. This “City Window” is turned 15° relative to the power plant and therefore provides an inner-city vista.

Power Plant in Düsseldorf
© Jens Kirchner

The steel-frame structure and thermal envelope of the halls comply with the normal standards applied to power plant construction. Only the outer skin was adapted by the architect and constructed from silver-coloured coated steel structural liner trays. The recessed joints consist of black perforated sheet metal plates with a white refracting surface, which is illuminated from the sides at night by fluorescent tubes. The light-coloured frame with dark joints reverses its look at night and turns into a symbolic light sculpture of vertical bands of light.

Structural Concept »City Window«

The size and the two glazed main facades of the 60-m-high and 38-m-wide “City Window” ensure it is the most structurally challenging element of the power plant envelope. Buildings that were viewed by the operator as not essential for the functioning of the plant had to be detached from the boiler house and stack. For this reason, a 40-m-high opening was cut in the facade facing the power plant, which is connected to the boiler house by movement joints only. In addition to ten smoke extraction openings, the roof surface has a circular hole for the stack but makes no direct contact with it.

Stiffening

The inside of the rectangular cuboid is mostly empty, with no structural elements providing paths for transferring loads into the foundations. The two glazed main facades also contribute no stiffness to the structure. A northern stairwell core provides north-south stiffening alone, The cross-braced roof and an adjacent full-height steel-frame structure stiffen the main structure torsionally and in the east-west direction.

A 3D structural analysis using the response spectrum method showed that wind was the critical load for the stiffening system in both main axes, but all structural connections were designed to resist earthquake loads.

Vertical load transmission

All vertical loads are carried by the steel columns and the reinforced concrete core. The structural members above the opening in the facade facing the power plant transfer their loads through a truss into the flanking columns – with the building corner stiffened by a narrow trussed girder.

“Stator”

A solid wall in front of the glass facade takes up the direction of the power plant again and forms its architectural termination. This component is internally stiffened by cross-bracing. However, the facade columns are relatively flexible in the transverse direction and cannot transfer force onto the main building body. The “stator” therefore contributes hardly anything to the stiffening system, but influences the building’s dynamic structural behaviour.

Reinforced concrete core / in-built components

The stairwell core was slip-formed in reinforced concrete. The reinforcement gradually reduces with height. Pockets were left for the prefabricated staircases and landings to be subsequently lifted into place in the stairwell.

Connection fittings were precisely cast into the core during the slip-forming process to allow connection to the steel facade. This required particular care because the 25-cm-thick wall panels of the core towards the top have only a limited capacity to accommodate bending moments. After installation, braces and bolts are welded onto connection plates cast into the integrated building components to carry the loads from the beams.

The facade beams continue at a distance of approximately 60 cm from the narrow core sides and are each supported at two points on the wall. The beams do not transfer the compressive and tensile forces and horizontal forces directly but are bolted to a spreader beam. Each end of the spreader beam has steel plates to transfer compression forces and is held in place by a hook plate. The intermediate spreader beam minimises the lever arm in the transfer of the load into the concrete and provides the means of making adjustments during steelwork erection.

Architecture
kadawittfeldarchitektur
Location
Düsseldorf (DE)

  • Paul Van Ostaijen Culture Campus in Leuven

    Lava architecten transformed an old mission building in Leuven into a place where circus arts, music, theatre, and dance coexist under one shared roof. Effective soundproofing is the precondition for the shared use of the facility.

  • The Lost Shtetl Museum in Lithuania

    The Jewish Museum in Šeduva commemorates the culture of Eastern European towns before World War II. With their building, Lahdelma & Mahlamäki Architects from Finland reimagine the small-scale structure of one such village. Its residents were murdered in 1941 by Nazis and their local collaborators.

  • Resembling a bridge, the scaly armour of the UCCA Clay Museum spans across the passageways to the neighbouring buildings. Where this structure touches the ground, Kengo Kuma & Associates arranged shallow water basins.

    Museum of Ceramic Art in Yixing

    The new UCCA Clay Museum advances the millennia-old tradition of artisanal ceramics the Chinese metropolis Yixing is renowned for. An armour of red clay tile encloses the exhibition spaces and the open timber roof constructions above them – an expressive space for the presentation of modern ceramic art.

  • The fly tower of the Glasshouse Theatre consists of textured prefabricated concrete elements, while the ­existing QPAC displays smooth in-situ concrete. The continuity of colouration, however, is clearly visible.

    Glasshouse Theatre in Brisbane

    The Glasshouse Theatre adds a fifth venue to the heritage-listed Queensland Performing Arts Centre. It can be flexibly used for concerts, operas, and dance and theatre performances. The glass facades of the deeply cantilevered foyer visualise the theatrical art of illusion on the exterior.

  • The monastery originally comprised four wings and a cloister. In the south, a squat church with a single nave connects to the complex. The head building with its three apses, a bell tower, and a transept were added in the 13th century.

    Monastery of Santa María of Sijena

    In their restoration of the Monastery of Santa María of Sijena, Pemán y Franco and Sebastián preserve traces of destruction, rebuilding, and decay spanning 800 years. Recently, they remodelled the east and north wings into an exhibition space for the convent’s valuable artworks.

  • The medical facility features a separate entrance in the east. A pergola made of prefabricated concrete elements welcomes the clients.

    Overnight Shelter and Medical Facility in Munich

    Housing for the homeless often consists of stacked contain ers. While the overnight shelter designed by Hild und K utilises prefabrication, thoughtful details adorn the robust building through which the Munich-based office conveys impres sions of warmth and home.