Queensferry Crossing near Edinburgh

Opened in September 2017, the Queensbury Crossing road bridge spans the Firth of Forth and connects Edinburgh with northern Scotland. It replaces an overloaded suspension bridge constructed in 1964, which will in future carry only buses, cycles and pedestrians. Together with the world-famous red cantilever railway bridge from 1890, they form a unique ensemble of bridge structures from three centuries.

Queensferry Crossing near Edinburgh
© Transport Scotland

The decision to adopt an inclined cable-stayed bridge was based on economy, functional requirements and topographical circumstances: a rock projecting out of the water offered a potential support in the middle of the firth. Because the engineers – not least out of aesthetic considerations – were seeking a symmetrical overall solution, they eventually settled on 2× 650 m main spans, which also provided the required shipping navigation openings. This determined the position of the two outer towers and the approach viaduct on the southern side. With a total length of 2.64 km, the structure is the longest three-tower, inclined cable-stayed bridge in the world.

Overall concept of the structure

A characteristic feature of the structure is the two diamond-patterned areas of the bridge elevation where opposing triangular fans of cables overlap. This detail provided the answer to a fundamental problem for multi-span inclined cable-stayed bridges: with single- or two-tower bridges, the towers are tied back by anchor cables, usually to stiff, land-side secondary spans. With three towers, this option for stabilisation is not available for the middle tower. Possible solutions include a very stiff deck, very stiff towers or various forms of guys. With the Queensferry Crossing, the stiffness of the whole system is increased by overlapping the inclined stays in the centre of the two main spans.

Bearing support concept

The middle tower is monolithically connected to the superstructure and carries all the loads arising from the carriageway in this area (Fig. B). The outer towers, on the other hand, are separated from the superstructure by a 70 cm gap, to avoid strains imposed by temperature changes. The superstructure is supported exclusively by the cables, while horizontal forces from wind are transmitted through integral bearings into the towers (Fig. C). Because of these sliding bearings, torsion in the superstructure arising from eccentric traffic loads or wind is resisted by the inner bridge piers S1 and N1. To combat uplift forces here, the bridge superstructure is tied down onto these V-shaped piers with a prestressing force of 2× 51 MN (Fig. D). Expansion joints are provided at the two abutments only, with the result that the movement at the southern abutment, which is 1,560 m from the fixed point at the middle tower, amounts to 2,270 mm.

Construction elements

The superstructure in the length supported by cables is a three-cell composite cross-section composed of a 30 m wide steel box beam and 5 m projecting concrete slabs on either side. Four longitudinal webs form the central spine, which carries transverse frames at 4.05 m centres. The cables from the middle tower are anchored to the inner side of the two inner webs; the cables from the two outer towers are attached to their outer sides. This offset arrangement allows the cables to be overlapped. The concrete slab at carriageway level is prestressed transversely to prevent cracking due to the centralised cable anchorages and the reduction in torsional stiffness this would otherwise produce.

The 202 m and 210 m high towers have an upwardly tapering reinforced concrete cross section with a maximum wall thickness of 2.40 m. The cables are anchored by steel hollow boxes with shear studs cast compositely into the concrete in the upper part of the towers (Fig. G).

A total of 288 inclined cables each consist of bundled seven-wire parallel strands. The least number of strands in any cable is 45. This is the shortest cable on the middle tower. In contrast, the shortest cables on the two outer towers carry the largest loads and are therefore the “thickest” cables with 109 strands. The loads on the towers, cables and superstructure were much greater during construction than after the bridge was complete.

Construction

While the middle tower was founded on rock protruding out of the water, up to 30 m diameter caissons were required for the outer towers and the first anchorage pier on the southern approach viaduct. The towers themselves were constructed using internal and external climbing forms in 54 lifts of up to 4 m in height. The inner climbing form was replaced by steel hollow boxes in the area of the cable anchorages.

The maximum 16.20 m long steel elements for the superstructure were prefabricated in China and brought to Scotland by sea. The concrete for the top slab supporting the carriageway came from a mixing plant specially set up for the project in the nearby port of Rosyth. An over 80 m tall floating crane installed the first four segments of the superstructure and a temporary working platform along with the two traveller cranes eventually required for the cantilever superstructure construction at each of the three towers. After the starter segments of carriageway slab were constructed in situ as a special case, they were attached to the first cables and lifted by the working platform. This was followed by the cyclic process of constructing the cantilever superstructure: the superstructure segments were positioned on pontoons, then lifted using the traveller cranes to the installation level, aligned, fixed in place with bolted interlocking plates, welded and then the cables attached. Now the traveller crane can move to the new front edge of the superstructure to lift the next segment.

Just before the final segment filled the gap in the main span, the middle tower had 322 m of superstructure cantilevering to either side, making it the world’s largest structure of this kind. Wind load calculations were very important at this stage of construction. Because the natural frequency periods of the middle tower in the computer model were calculated as greater than 11 s, resonant oscillations and deformations at the end of the superstructure of 0.9 m horizontally and 2.0 m vertically had to be taken into account. Inclined anchor cables were installed between the superstructure and the foundation to reduce the bending moment in the tower with the structure in this condition.

The ends of the cantilevering superstructure were brought to the correct level and alignment before the final segment could be installed. The strands of the cables still to be installed at that stage provided the required 700 t ballast.

The last closure segment was put in place in February 2017; the bridge was opened by the Queen on 4 September 2017.

Location
Edinburgh (GB)

  • Paul Van Ostaijen Culture Campus in Leuven

    Lava architecten transformed an old mission building in Leuven into a place where circus arts, music, theatre, and dance coexist under one shared roof. Effective soundproofing is the precondition for the shared use of the facility.

  • The Lost Shtetl Museum in Lithuania

    The Jewish Museum in Šeduva commemorates the culture of Eastern European towns before World War II. With their building, Lahdelma & Mahlamäki Architects from Finland reimagine the small-scale structure of one such village. Its residents were murdered in 1941 by Nazis and their local collaborators.

  • Resembling a bridge, the scaly armour of the UCCA Clay Museum spans across the passageways to the neighbouring buildings. Where this structure touches the ground, Kengo Kuma & Associates arranged shallow water basins.

    Museum of Ceramic Art in Yixing

    The new UCCA Clay Museum advances the millennia-old tradition of artisanal ceramics the Chinese metropolis Yixing is renowned for. An armour of red clay tile encloses the exhibition spaces and the open timber roof constructions above them – an expressive space for the presentation of modern ceramic art.

  • The fly tower of the Glasshouse Theatre consists of textured prefabricated concrete elements, while the ­existing QPAC displays smooth in-situ concrete. The continuity of colouration, however, is clearly visible.

    Glasshouse Theatre in Brisbane

    The Glasshouse Theatre adds a fifth venue to the heritage-listed Queensland Performing Arts Centre. It can be flexibly used for concerts, operas, and dance and theatre performances. The glass facades of the deeply cantilevered foyer visualise the theatrical art of illusion on the exterior.

  • The monastery originally comprised four wings and a cloister. In the south, a squat church with a single nave connects to the complex. The head building with its three apses, a bell tower, and a transept were added in the 13th century.

    Monastery of Santa María of Sijena

    In their restoration of the Monastery of Santa María of Sijena, Pemán y Franco and Sebastián preserve traces of destruction, rebuilding, and decay spanning 800 years. Recently, they remodelled the east and north wings into an exhibition space for the convent’s valuable artworks.

  • The medical facility features a separate entrance in the east. A pergola made of prefabricated concrete elements welcomes the clients.

    Overnight Shelter and Medical Facility in Munich

    Housing for the homeless often consists of stacked contain ers. While the overnight shelter designed by Hild und K utilises prefabrication, thoughtful details adorn the robust building through which the Munich-based office conveys impres sions of warmth and home.